In a renewable energy substation, switchgear downtime is never just a maintenance cost. Every hour the plant cannot export is generation you cannot sell. That is why the usual advice on aging switchgear, "just swap the breakers", is only half useful. It assumes your cubicles are still sound and that the original manufacturer still supports them. Many owners of 10 to 15-year-old plants have neither.
This article works through a typical retrofit decision from the outage window backwards. It also states plainly when new withdrawable panels make sense, and when they do not.

The Scenario: A 12-Year-Old Solar Plant
Assume the following:
- The plant was commissioned about 12 years ago. It has older fixed-type 35 kV collector cubicles and a fixed-type 0.4 kV auxiliary and station-service distribution board.
- Breaker operating mechanisms are wearing, and spare parts for the original model now take months to arrive.
- After a capacity extension, the prospective fault current at the 35 kV bus is 31.5 kA (assumed), above the 25 kA rating of the existing cubicles.
- The grid operator approves one planned outage of 5 days (assumed).
- The switchgear room cannot be extended.
The owner's question is a procurement question: swap breakers, replace some panels, or replace the whole lineup?
Why Renewable Substations Age Differently
Three pressures make these sites harder on switchgear than a typical factory.
- Downtime is tied directly to revenue. A Siemens reference project describes an arc fault that destroyed a wind substation's medium-voltage system and stopped four connected wind farms, with turnover losses of roughly 500,000 euros per month.
- Switching duty is heavy. Reactive-power compensation means frequent capacitor and reactor switching. T&D World reports that breaker failures during capacitor and reactor switching are among the most common electrical failures at SDG&E substations, even in modern designs.
- Spares and people are far away. In Eaton's published Gaston hydro retrofit case, spare parts were becoming hard to obtain and breaker overhauls needed an outage of up to a week. Remote renewable sites feel this even more.
Step 1: Let the Outage Window Choose the Method
|
Option |
Typical outage |
Works best when |
Watch out for |
|---|---|---|---|
|
Breaker-level retrofill |
ABB guidance: about 1–2 hours per breaker |
Enclosure and busbars are sound, ratings are adequate, and the OEM offers a kit |
Does not fix corrosion or a rating shortfall |
|
Phased panel replacement |
Depends on your cutover design |
Some panels have rating or compartment problems and spares are gone |
New panels must match busbar height and cable entry |
|
Full lineup replacement |
ABB guidance: more than 5 days |
Enclosure is damaged or corroded, ratings are too low, or no retrofill kit exists |
Longest outage; needs a rehearsed cutover |
Here is the honest part, even though we are a cabinet manufacturer. If your window is a day or two and your OEM sells a retrofill kit for your cubicle, buy the kit, not new cabinets. New panels earn their place in four cases:
- No kit exists because the design is obsolete or from a local brand.
- The enclosure is corroded, or was damaged by an arc fault.
- The new fault level exceeds the existing rating.
- You want drawout construction so that future maintenance no longer needs a full section outage.
- In our scenario, cases 3 and 4 apply, so the owner moves to panel replacement.
Cost control tip: published savings claims for retrofit versus replacement range from about 40% to 70%, and they rarely state their assumptions. Do not budget from them. Build your own comparison: equipment, installation, and the lost generation during the outage.
Step 2: Low-Voltage Side, From Fixed to Withdrawable
A fixed-type panel has its breaker wired permanently in place, so servicing one feeder usually means de-energizing the section. A withdrawable (drawout) design puts each functional unit on a drawer or carriage that can be pulled out to a test or withdrawn position.
For the 0.4 kV auxiliary board, the owner specifies a 【Withdrawable Cabinet】, in this case the GCS type. Published parameters of Gangheng's GCS low voltage withdrawable switchgear that matter for this job:
- Rated voltage 380 (400, 660) V and horizontal busbar current up to 4000 A
- Busbar short-time withstand of 50 or 80 kA for 1 s
- Height 2200 mm, widths of 400, 600, 800 or 1000 mm, depth of 800 or 1000 mm
- Drawer height module of 160 mm; one MCC cabinet holds up to 11 single-unit or 22 half-unit drawers
- Drawer panels show open, closed, test and withdrawn positions
- Drawout and fixed units can be combined, and the cabinet connects to dry-type or oil-immersed transformers
- Protection degree IP30 or IP40, for ambient temperatures from -5°C to +40°C and altitudes up to 2000 m
That last line matters at desert and highland sites. If the room is hotter, dustier or higher, tell the supplier before the design is frozen. Because the existing room is fixed, width and depth modules are the first thing to check against the floor plan.
Step 3: The 35 kV Side, Metal-Clad Switchgear
In metal-clad switchgear, the breaker, busbar and cable sections each sit in separate grounded metal compartments, so a fault in one is less likely to spread to the others.
The owner needs 31.5 kA, so the existing 25 kA design is out. A 【Metal Clad Switchgear】 such as Gangheng's JYN1-40.5 lists these parameters:
- Rated voltage 40.5 kV, with 1250, 1600 or 2000 A current options
- Short-circuit breaking current of 25 or 31.5 kA, and peak withstand of 63 or 80 kA
- Protection degree IP2X
- Listed dimensions of 1818 × 2400 × 2925 mm (W × D × H)
- Interchangeable withdrawable trucks for circuit breaker, isolating, lightning arrester, voltage transformer and station service transformer units
- Rated for -15°C to +40°C and up to 1000 m altitude, with an optional anti-condensation controller for humid sites
Two details deserve attention. First, the 2925 mm height and 2400 mm depth must be checked against the ceiling, the cable trench and the cable-entry positions of the old line-up. Second, pick the 31.5 kA option and ask for the type test report, not just the nameplate value. If your site is above 1000 m, ask for an engineering review before ordering.
The product page also lists wind and solar stations among typical applications, and states that the cabinet suits both new builds and retrofit projects.
Step 4: The Data Pack to Send Before You Order
Most retrofit delays start with missing information, not with manufacturing. Prepare:
- One-line diagram and circuit scheme numbers, plus the auxiliary circuit schematics
- Room drawing: dimensions, ceiling height, cable trench and entry positions, door width for moving panels
- Short-circuit capacity calculation and the relay protection setting sheet
- Component list, existing CT ratios, and surge arrester requirements
- Site conditions: altitude, temperature range, humidity, dust or salt exposure
- Standard: Gangheng builds to Chinese national standards by default, and can build to ANSI/IEEE or BS on request
Gangheng also accepts non-standard work such as wider cabinets, special busbar schemes and special secondary circuits. Customization usually adds cost depending on what changes, so ask for the difference to be quoted separately.
Step 5: Plan the Cutover Around the 5-Day Window
In the scenario, the owner schedules it like this:
- Before the outage: panels are built, factory-tested and shipped. The owner witnesses the factory tests.
- Outage days 1–2: old panels are isolated and removed; new LV panels are set and connected.
- Outage days 3–4: the 35 kV line-up is installed, cabled and tested with protection settings loaded.
- Day 5: insulation tests, protection checks, then re-energization.
The schedule is only believable if the supplier can support it. Three supplier facts worth confirming in writing:
- Lead time depends on order size. Gangheng's company information puts it at roughly 30 to 60 days, so confirm per project.
- There is no minimum order quantity, so a single replacement line-up is accepted.
- Site support: Gangheng offers video-guided installation, and reports that for a Tanzania KYN61-40.5 project, the time from unboxing to energization was 5 days.
Warranty is 12 months after acceptance, and the company states it remains responsible for hidden defects for 5 years after that.
Common Pitfalls
Comparing panel prices only. Include outage cost, or the cheapest quote can be the most expensive project.
Skipping the room survey. A cabinet that does not fit the cable trench costs days.
Trusting the old nameplate. Recalculate the fault level after every plant extension.
Ignoring the environment. Humidity, dust and altitude should be in the RFQ, not discovered at commissioning.
Forgetting spares. Ask which breaker and relay brands are used, and whether they are still in production.
Summary: What to Do Next
- Get the outage window in writing first. It decides everything else.
- Check whether an OEM retrofill kit covers your cubicles. If it does and the enclosure is sound, use it.
- If ratings, corrosion or obsolescence rule that out, specify withdrawable panels for LV and metal-clad switchgear for 35 kV.
- Send the full data pack in one go, and confirm lead time, standards and site support in writing.
- Rehearse the cutover on paper before the outage day.
Need a quotation or a drawing check? Send your one-line diagram and room dimensions to Gangheng Electric for a technical review.

FAQ
- How long does switchgear last before it needs retrofit or replacement? Many lineups run beyond 20 to 25 years. The real trigger is usually not age itself but spare-part availability, rising fault levels, corrosion and maintenance cost.
- Should I retrofit or replace aging switchgear? If the enclosure and busbars are sound, ratings are adequate and an OEM kit exists, retrofill is usually faster. If the enclosure is damaged, the rating is too low, or no kit exists, replacement is the safer long-term choice.
- What is the difference between withdrawable and fixed switchgear? In fixed switchgear, the breaker is permanently installed. In withdrawable switchgear, the breaker or functional unit can be moved to a test or withdrawn position, which makes inspection and replacement of a single unit simpler.
- How long is the outage for a switchgear upgrade? It depends on the method. ABB guidance puts a breaker swap at about 1 to 2 hours per breaker, and a full lineup replacement at more than 5 days. Plan from your approved outage window.
- Can new cabinets be built to fit an old switchgear room? Often yes. Gangheng can customize cabinet width, busbar scheme and secondary circuits. Send your room drawing and one-line diagram early so fit can be checked before ordering.